回复: [edk2-rfc] release candidate tags
gaoliming
Laszlo:
toggle quoted message
Show quoted text
I understand this release requirement. Now, we have Feature Planning Freeze (1WW), Soft Feature Freeze (1WW) and Hard Feature Freeze (5 days). I would propose to remove Feature Planning Freeze, keep Soft Feature Freeze (1WW), and extend Hard Feature Freeze (1week and 5 days). For Q3 stable tag, new planning will be like the below. Date (00:00:00 UTC-8) Description 2021-05-28 Beginning of development 2021-08-09 Soft Feature Freeze 2021-08-16 Hard Feature Freeze 2021-08-27 Release Thanks Liming -----邮件原件----- |
|
Laszlo Ersek
On 06/25/21 04:11, gaoliming wrote:
Laszlo:I haven't even been aware of the "planning freeze". I think we can remove it. Regarding the HFF, I'd really suggest / request 14 calendar days. Thanks Laszlo
|
|